Contact Us
Project Timeline & Payments
1
Step 1
Select your finishes:
- Cabinets
- Quartz countertop
- Sink
- Knobs, handles, and pulls
Schedule on-site design session: $350
- Viewing of selected kitchen cabinet sample
- Take room measurements
- Delivery of blueprints for your review (up to three modifications included)
2
Step 2
Sign the contract
Deposit amount: 20%
Example: For a 12 cabinet ($12,000) package, the deposit will be $2,400
3
Step 3
Construction Day 1
- Dust containment
- Demolition
- Progress payment: 20%
Construction Day 2
- Install cabinets
- Install cabinet knobs, handles, and pulls
- Progress payment: 20%
Construction Day 3
- Install quartz countertop
- Install sink
- Progress payment: 20%
Construction Day 4
- Final installation
- Cleaning
- Progress payment: 20% (Final balance)
Construction Day 5+ (Optional)
Additional options selected and scheduled for your remodeling project